Engineering excellence from survey to completion

Contract data, scope of works, structure progress and site mobilization for the Satai Ghat–Chowka four-laning project, Package-3, NH-34.

Contract data

Project fact sheet

Name of projectFour-laning of near Satai Ghat (Darguwan) to Chowka (Matguwan) Section of NH-34, D. Ch. 89+875 to D. Ch. 145+000 (Total 55.125 km), Madhya Pradesh (Package-3), Hybrid Annuity Mode
Client / AuthorityNational Highways Authority of India (NHAI)
Independent EngineerM/s Chaitanya Projects Consultancy Pvt. Ltd. J/V M/s Geo Designs & Research Pvt. Ltd.
ConcessionaireM/s Sataighat Chowka Bageshwar VRS Highway Pvt. Ltd.
ContractorVelji Ratna Sorathia Infra Pvt. Ltd. (VRS Group)
Project length55.125 km
Project bid cost₹614.09 Cr (₹6,14,09,43,000)
LOA number & dateMPDIV21/14/2024-MP Division (E-file No. 269157), dated 07.01.2025
Concession Agreement date11 March 2025
Appointed date27 October 2025
Construction period730 days from Appointed Date (24 months)
Scheduled completion date26 October 2027
O&M period15 years from the date of COD
Salient features

Pavement composition & structures

Pavement composition (mm)
Section Stretch (km) Sub-grade GSB WMM DBM BC
Main Carriageway (MCW) 55.125 500 200 190 50 40
Service Road 41.83 500 200 150 — 40
New / widened structures & facilities
Description Scope Unit Quantity
Minor BridgeRetained & widenedNos.11
Minor BridgeNew constructionNos.08
Vehicular Underpass (VUP)New constructionNos.10
Light Vehicular Underpass (LVUP)New constructionNos.10
Small Vehicular Underpass (SVUP)New constructionNos.02
Box CulvertReconstruction / widening / newNos.69
Hume Pipe CulvertWidening & cross roadNos.50
Fly OverNew constructionNos.01
Minor JunctionNew constructionNos.32
Thrie-beam crash barrierSingle faced, metalKm.107.454
RCC DrainRoadside drainageKm.44.880
Progress status

Project milestones & physical progress

Overall physical progress achieved to date: 50.23% (October 2026 MPR).

Project milestones (Concession Agreement)
MilestoneDaysPhysical progress (%)Scheduled datePhysical progress achieved
Milestone I18020%25-04-2026Achieved on 15.04.2026
Milestone II36035%26-10-2026Achieved on 30.06.2026
Milestone III55075%30-04-2027In progress
Milestone IV730100%26-10-2027—
Payment during construction period
Payment milestoneOn achievement ofRemarks
1st Payment Milestone5% Physical ProgressAchieved on 31.01.2026
2nd Payment Milestone10% Physical ProgressAchieved on 28.02.2026
3rd Payment Milestone20% Physical ProgressAchieved on 15.03.2026
4th Payment Milestone30% Physical ProgressAchieved on 30.05.2026
5th Payment Milestone40% Physical ProgressAchieved on 08.08.2026
6th Payment Milestone50% Physical ProgressAchieved on 31.10.2026
7th Payment Milestone60% Physical ProgressIn progress
8th Payment Milestone70% Physical Progress—
9th Payment Milestone80% Physical Progress—
10th Payment Milestone90% Physical Progress—
Mobilization

Plant, equipment & organization

Key plant & equipment deployed

Category Nos.
Excavator (320-class)24
Hyva tipper — 10 wheel88
Hyva tipper — 12 wheel50
Motor Grader12
Soil Compactor10
Back Hoe Loader9
Hydra Crane8
Transit Mixer11
RMC Plant2
WMM Plant1
Sensor / Vogele Paver1
Water Tanker15

Full deployment spans 42 categories of machinery—from crushers and DG sets to survey and safety equipment.

Organization on site

The concessionaire's site team is led by a Senior General Manager and Project Manager, supported by dedicated Highway, Structures, Survey, QA/QC, Planning, HR and Store teams.

  • Manager (Highway) → Dy. Highway Manager → Site Engineers
  • Dy. Project Manager (Structures) → Structure Engineers
  • Survey Manager → Survey Team
  • Material Engineer → QA/QC Laboratory Team
  • Store Manager → Store & Weighbridge Staff
  • Safety Officer · Mechanical In-charge · HR Manager

Want the full Monthly Progress Report?

Reach out to the project team for detailed MPR documentation, drawings and correspondence status.

Contact the project team →