NHAI · NH-34 · Package-3

Engineering the Satai Ghat–Chowka Corridor

Four-laning of near Satai Ghat (Darguwan) to Chowka (Matguwan) Section of NH-34 — a 55.125 km Hybrid Annuity Mode highway under construction across Sagar & Chhatarpur districts, Madhya Pradesh.

55.125 kmProject length
HAMHybrid annuity mode
₹614.09 CrProject bid cost
Under ConstructionCurrent status
About the project

Four-laning NH-34 across the Sagar–Chhatarpur corridor

The Government of India, through the National Highways Authority of India (NHAI), has entrusted the development, maintenance and four-laning of the Satai Ghat (Darguwan) to Chowka (Matguwan) section of NH-34 — from Design Chainage 89+875 (Existing Km 90.299) to Design Chainage 145+000 (Existing Km 143.663), a total length of 55.125 km — in the State of Madhya Pradesh, executed as Package-3.

The corridor forms part of the wider Kanpur–Sagar economic corridor, improving connectivity through Sagar and Chhatarpur districts, reducing travel time and vehicle operating costs, and strengthening the national highway network for the efficient movement of goods and passengers.

  • New construction of a 4-lane divided carriageway with service roads (41.83 km)
  • 1 Fly Over, 19 Minor Bridges and 22 underpasses (VUP / LVUP / SVUP)
  • 95 box & Hume pipe culverts, RS/RE retaining walls, and road-side drainage
  • Toll plaza, way-side amenities, highway lighting and safety furniture
Project corridor location map — Madhya Pradesh, Kanpur–Sagar economic corridor
Delivered by

A VRS Group Company

The project is being executed by M/s Sataighat Chowka Bageshwar VRS Highway Private Limited as Concessionaire, with construction carried out by Velji Ratna Sorathia Infra Pvt. Ltd. (VRS/VRSIPL) — part of the VRS Group of infrastructure companies engaged in highway, bridge and EPC construction across India.

On site, the VRS team is supported by a dedicated Independent Engineer — M/s Chaitanya Projects Consultancy Pvt. Ltd. in joint venture with M/s Geo Designs & Research Pvt. Ltd. — appointed by NHAI to supervise and certify the quality and progress of works.

0 Km of NH-34
0+ Engineers & staff on site
0 Plant & equipment categories
24 Month construction period
Project highlights

What we are building

Schedule-B of the Concession Agreement defines a full-spectrum four-laning scope — from earthwork and pavement to major structures and road-side facilities.

🛣

Fly Over & Underpasses

1 Fly Over and 22 underpasses — 10 VUP, 10 LVUP and 2 SVUP — for safe, grade-separated cross movement.

🏗️

Minor Bridges

19 minor bridges — 11 retained & widened, 8 newly constructed — along the 55.125 km alignment.

🛣️

Service Roads

41.83 km of service roads alongside the main carriageway, providing local access and safer traffic separation.

💧

Culverts & Drainage

95 box & Hume pipe culverts and 44,938 running metres of RCC drain for effective cross-drainage.

Project milestones

Concession Agreement schedule

Appointed Date: 27 Oct 2025 · Construction Period: 730 days (24 months) · Scheduled Completion: 26 Oct 2027

MS-I

20% Physical Progress

180th day · 25 Apr 2026
Achieved 10.10%Target 20%
MS-II

35% Physical Progress

360th day · 26 Oct 2026
In progressTarget 35%
MS-III

75% Physical Progress

550th day · 30 Apr 2027
ScheduledTarget 75%
MS-IV

100% — Completion

730th day · 26 Oct 2027
ScheduledTarget 100%

See detailed progress & S-curve →

Site mobilization

Plant, equipment & manpower on site

42 categories of construction plant are deployed across the corridor, backed by a 70-plus strong engineering and support team.

20Excavators (320-class)
118Hyva tippers (10 & 12-wheel)
2RMC batching plants
9Motor graders
10Soil compactors
3Vibratory rollers (SDR)
1WMM plant
10Water tankers (12,000L)
From the field

Gallery preview

Geo-tagged construction photographs captured monthly across the corridor.

View full gallery →